Owner: Summit Materials
General Contractor: S. M. Wilson
Concrete Contractor: Ahal
The above photo is of the Continental cement dome foundation. Raineri, along with another concrete producer, started the 1,800 cubic yard placement at 3 am. Ahal Contracting utilized two of its Putzmeister pumps and a telebelt conveyor to handle the 300 yard per hour placement rate, and by 9 am the pour was complete.